Installing a home charger: what affects the cost
The wallbox is only part of the bill. The rest depends on your home: how far it is from the fuse box to the parking spot, what the main fuse can handle, and which grid you have. We don't give kroner amounts, because prices vary a lot between electricians and places. Instead, here is what decides the price, so you can compare quotes.
1. Distance and cable route
What most often separates a simple installation from an expensive one is the route the cable has to take. The charger needs its own circuit with its own cable from the fuse box.
- Length: a longer cable costs more, and over long distances the cable must be thicker.
- Route: along the outside of a wall is quickest. Through several rooms, floors or insulated walls takes longer.
- Detached garage or carport: the cable often has to be buried, or there may already be a cable out there that can be used. Ask the electrician whether it has enough capacity.
2. Space in the fuse box
The new circuit needs room for a circuit breaker and an RCD. If the fuse box is full, it must be extended. Older fuse boxes with screw-in fuses often have to be replaced entirely before a charger can be connected, which makes the job much bigger. Take a photo of the fuse box and send it with your quote request.
3. The main fuse and load balancing
The main fuse limits how much power the whole house can draw at once. A charger at full power uses a lot of it. There are two ways to deal with that:
- Load balancing: the charger measures what the rest of the house uses and turns charging down when needed. Almost every charger supports it, but some need an extra meter in the fuse box. Ask whether it's in the quote.
- Upgrading the main fuse: must be agreed with the grid company and may need a new service cable. It's rarely needed just for an EV charger.
We assume the charger can use about 60 % of the main fuse. With a 40 A main fuse that leaves 24 A for the charger, which is more than enough to fill the battery overnight. Enter your main fuse under "My home" at the top of the page to see what you get. See how we calculate with the fuses.
Remember the grid tariff too: it has a capacity component based on the hours with the highest power use each month. Charging at night, when the rest of the house uses little, keeps the peaks down. More in the guide to main fuses and load balancing.
4. IT grid or TN grid
The grid decides which breaker and cable the electrician installs:
| Grid | Breaker | Cable |
|---|---|---|
| TN 400V, 3 phases | 3-pole + N | 5 conductors (L1, L2, L3, N, PE) |
| IT 230V, 1 phase | 2-pole | 3 conductors (L1, L2, PE) |
| IT 230V, 3 phases | 3-pole | 4 conductors (L1, L2, L3, PE) |
On an IT grid most cars charge on 1 phase. Still, consider asking for a 3-phase cable: it's easier to lay now than to run a new one later, and a next car that supports IT 3-phase can then charge faster. Read more in which home charger to choose for an IT grid.
5. RCD protection
An EV charger needs protection against DC fault currents (6 mA DC). If the charger has it built in, a regular type A RCD is enough. If not, a type B RCD is required, which costs more. All 10 chargers we follow have it built in.
6. Charging cable and network
- Charging cable: 7 of 10 chargers have a Type 2 socket without a fixed cable. Then you need to buy a charging cable as well. The other 3 have a fixed cable.
- Network: most chargers use wifi or mobile data for the app, updates and load balancing. Check that there's coverage at the parking spot.
7. Housing co-ops and shared parking
In a housing co-op (borettslag) or condominium (sameie) you usually need approval from the board, and many choose a shared solution for the whole car park with shared load balancing and billing. The board then often collects the quotes. See charging in housing co-ops and condominiums. Of the chargers we follow, Easee Charge Core and Zaptec Pro are built for shared parking.
8. Rules and paperwork
- The charger must be installed by an electrical contractor registered in DSB's register of electrical contractors (Elvirksomhetsregisteret). You can look the company up there before you say yes.
- When the job is done, you should get a declaration of conformity (samsvarserklæring) documenting that the installation meets the regulations.
- The electrician notifies the grid company of the installation.
- Don't do it yourself. A faulty installation can cause a fire risk and problems with your insurance.
Checklist before you ask for quotes
- Grid type (IT or TN) and main fuse. It's in the fuse box, or ask the grid company.
- A photo of the fuse box, and of the route from the box to where the charger will go.
- Roughly how many metres the cable must run, and whether it must be buried.
- Which charger you want, or ask the electrician to suggest one. Check that it suits your car with us first, especially on an IT grid.
- Ask for a fixed price, and what's included: charger, cable, breaker, RCD, load balancing meter, app setup and any digging.
- Ask about a 3-phase cable, even if your car only uses 1 phase today.